LANE CLOSURES for US 80/FM 548 CONSTRUCTION

{click here}

LANE CLOSURES for US 80/FM 548 CONSTRUCTION.

September 1st - 3rd 2010

Please be aware between the dates of Sep. 1, 2010 and Sep. 3, 2010 the inside lane of West Bound US 80 will be temporarily closed. The closure is necessary for the safe entry and exit of truck traffic to the center median. Trucks will be hauling dirt to the center median in preparation for a future mainlane detour. This left lane of traffic will be closed from approximately one mile East of FM 548 to one mile West of FM 548 during the hours of 9:00 AM – 3:30 PM. Only minor delays are expected during the closure and both West Bound lanes will be reopened to traffic no later than 3:30 PM.

For more information, contact:
FORNEY ROADBUILDERS
402 East Brooks
Forney, TX 75126
972-552-2656 - Office
972-552-5847 - FAX
aaldridge@patetransportation.com

August 31st 2010

Please be aware that on Tuesday, Aug. 31, 2010, the inside lane of West Bound US 80 will be temporarily closed for repositioning the concrete traffic barrier. This left lane of traffic will be closed from approximately one mile East of FM 548 to one mile West of FM 548 during the hours of 9:00 AM – 3:30 PM. Only minor delays are expected during the closure and both West Bound lanes will be reopened to traffic no later than 3:30 PM.

For more information, contact:
FORNEY ROADBUILDERS
402 East Brooks
Forney, TX 75126
972-552-2656 - Office
972-552-5847 - FAX
aaldridge@patetransportation.com

August 30th 2010

Please be aware that on Monday, Aug. 30, 2010, the inside lane of East Bound US 80 will be temporarily closed for repositioning the concrete traffic barrier. This left lane of traffic will be closed from approximately one mile East of FM 548 to one mile West of FM 548 during the hours of 9:00 AM – 3:30 PM. Only minor delays are expected during the closure and both East Bound lanes will be reopened to traffic no later than 3:30 PM..

For more information, contact:
FORNEY ROADBUILDERS
402 East Brooks
Forney, TX 75126
972-552-2656 - Office
972-552-5847 - FAX
aaldridge@patetransportation.com

August 19th 2010

Please be aware that on Thursday, Aug. 19, 2010, the inside lane of West Bound US 80 will be temporarily closed for repositioning the concrete traffic barrier. This left lane of traffic will be closed from approximately one mile East of FM 548 to one mile West of FM 548 during the hours of 9:00 AM – 3:30 PM. Only minor delays are expected during the closure and both West Bound lanes will be reopened to traffic no later than 3:30 PM.

For more information, contact:
FORNEY ROADBUILDERS
402 East Brooks
Forney, TX 75126
972-552-2656 - Office
972-552-5847 - FAX
aaldridge@patetransportation.com

August 16-17th 2010

Please be aware that on Monday, Aug. 16, 2010 and Tuesday, Aug. 17, 2010, the inside lane of West Bound US 80 will be temporarily closed for restriping operations. This left lane of traffic will be closed from approximately one mile East of FM 548 to one mile West of FM 548 during the hours of 9:00 AM – 3:30 PM. Only minor delays are expected during the closure and both West Bound lanes will be reopened to traffic no later than 3:30 PM each day.

For more information, contact:
FORNEY ROADBUILDERS
402 East Brooks
Forney, TX 75126
972-552-2656 - Office
972-552-5847 - FAX
aaldridge@patetransportation.com

August 13th 2010

Please be aware that on Friday, Aug. 13, 2010, the inside lane of East Bound US 80 will be temporarily closed for restriping operations. This left lane of traffic will be closed from approximately one mile West of FM 548 to one mile East of FM 548 during the hours of 9:00 A.M. – 3:30 P.M. Only minor delays are expected during the closure and both East Bound lanes will be reopened to traffic no later than 3:30 P.M.

For more information, contact:
FORNEY ROADBUILDERS
402 East Brooks
Forney, TX 75126
972-552-2656 - Office
972-552-5847 - FAX
aaldridge@patetransportation.com

August 11th 2010

Please be aware that on Wednesday, August 11, 2010, the inside lane of East Bound US 80 will be temporary closed for restriping operations. This left lane of traffic will be closed from approximately one mile West of FM 548 to one mile East of FM 548 during the hours of 9:00 A.M. - 3:30 P.M. Only minor delays are expected during the closure and both East bound lanes will be reopened to traffic no later than 3:30 P.M.

For more information, contact:
FORNEY ROADBUILDERS
402 East Brooks
Forney, TX 75126
972-552-2656 - Office
972-552-5847 - FAX
aaldridge@patetransportation.com

July 29th 2010

Please be aware that on Thursday, July 29, 2010 traffic delays will be expected at the intersection of US 80/FM 548. During the hours of 9:00AM – 1:00PM, traffic signalization crews will be working on both sides of the intersection to activate a temporary signal system and to remove the existing signals. During this time, traffic will be directed through the intersection with the use of City of Forney police officers. The intersection and traffic should be returned to its current operating condition no later than 1:00 PM on the same day.

For more information, contact:
FORNEY ROADBUILDERS
402 East Brooks
Forney, TX 75126
972-552-2656 - Office
972-552-5847 - FAX
aaldridge@patetransportation.com

May 20th - June 4th 2010

A lane closure will be established daily on east bound US 80 for the installation of a temporary detour. Trucks hauling embankment material will be using the lane closure to access the existing median. The closure will extend from approximately ½ mile east of FM 740 (Pinson Rd) to ¼ mile east of FM 548. During the off peak traffic hours of 9:00AM-3:30PM the inside lane of traffic will be closed. All existing lanes will be reopened to traffic during the hours of 3:30PM-9:00AM.

Please expect minor delays during the hours of the lane closure.

For more information, contact:
FORNEY ROADBUILDERS
402 East Brooks
Forney, TX 75126
972-552-2656 - Office
972-552-5847 - FAX
aaldridge@patetransportation.com

May 10th - 11th 2010

Please note that there may be a need to temporarily close the inside lane of east bound US 80 for the installation of the cable barrier anchor section. If needed, the closure will extend from approximately ½ mile east of FM 740 (Pinson Rd) to ½ mile east of FM 548. During the off peak traffic hours of 9:00AM-3:30PM the inside lane of traffic may be closed. All existing lanes will be reopened to traffic during the hours of 3:30PM-9:00AM.

Please expect some minor delays if there exists a need to implement this closure.

For more information, contact:
FORNEY ROADBUILDERS
402 East Brooks
Forney, TX 75126
972-552-2656 - Office
972-552-5847 - FAX
aaldridge@patetransportation.com

May 5th 2010

A lane closure will be established on east bound US 80 for the completion of the temporary concrete traffic barrier and crash attenuator. The closure will extend from approximately ½ mile east of FM 740 (Pinson Rd) to ½ mile east of FM 548. During the off peak traffic hours of 9:00AM-3:30PM the inside lane of traffic will be closed. All existing lanes will be reopened to traffic during the hours of 3:30PM-9:00AM.

Please expect minor delays during the hours of the lane closure.

May 4th 2010

A lane closure will be established on west bound US 80 for the completion of the temporary concrete traffic barrier and crash attenuator. The closure will extend from approximately ½ mile east of FM 740 (Pinson Rd) to ½ mile east of FM 548. During the off peak traffic hours of 9:00AM-3:30PM the inside lane of traffic will be closed. All existing lanes will be reopened to traffic during the hours of 3:30PM-9:00AM.

Please expect minor delays during the hours of the lane closure.

For more information, contact:
FORNEY ROADBUILDERS
402 East Brooks
Forney, TX 75126
972-552-2656 - Office
972-552-5847 - FAX
aaldridge@patetransportation.com

April 23rd – 30th

A lane closure will be established on west bound US 80 for the installation of concrete traffic barrier. The closure will extend from approximately ½ mile east of FM 740 (Pinson Rd) to ½ mile east of FM 548.

During the off peak hours of 9:00AM – 3:30PM the inside lane of traffic, in the west bound direction only, will be closed. All existing lanes will be reopened to traffic during the hours of 3:30PM – 9:00AM.

Please expect delays during hours of the lane closure.

For more information, contact:
FORNEY ROADBUILDERS
402 East Brooks
Forney, TX 75126
972-552-2656 - Office
972-552-5847 - FAX
aaldridge@patetransportation.com

March 11th – 15th

There will be a lane closure on the East Bound Frontage Road of US80 approximately 1/2 mile East of FM740 and it will extend all the way to FM548. The lane closure will be for the outside lane of traffic only and it will start at 9:00am and will last until 3:30pm. This closure is for the installation of concrete traffic barriers which will remain in place throughout the first phase of construction.

For more information, contact:
FORNEY ROADBUILDERS
402 East Brooks
Forney, TX 75126
972-552-2656 - Office
972-552-5847 - FAX
aaldridge@patetransportation.com